Panipat Refinery Greenfield Catalyst Manufacturing Unit Project: What is next?
Mar 18: 8Project Name: Panipat Refinery Greenfield Catalyst Manufacturing Unit Project
8Project Cost: Rs 206 crore
8Project Description:  PDIL and Honeywell UOP are involved. The detailed feasibility report was prepared by PDIL. Currently, planning related activities are on. 30% of the model review has been completed, and all P&ID finalized and issued for engineering. At present site enabling work as well as investigation and geotechnical survey work are going on. 39 out of 68 vessels has already been ordered. Further RFQs are expected soon.
8Project Event: RFQ for the rest of the vessels and mounded bullets is expected by May 2019.
8Expenditure Approval: Q4:2016
8RFQ Date: May/2019
8Release Date: May/2019
8Start Date: Q4:2018
8Completion Date: Q2:2020
Click here for more details
8A shutdown of a gasoil hydrotreating unit is coming up