Mar 13: Project Name: Greenfield Super Thermal Power Project
8Project Cost: 16000 crores
8Project Description: The EPC contractor BHEL is executing civil works in a greenfield super-critical thermal power project.
8Foundation stone for the project has been laid.
8A captive coal jetty is under construction for the thermal power complex.
8What kind of RFQs are expected for the captive coal jetty
8Find out tenders expected from BHEL
Click here for more details for project details and key contacts

8Project Name: Greenfield Super Thermal Power Project
8Project Cost: 15000 crores
8Project Description: A super-critical thermal power project has been fully commissioned.
8But, still works are pending at the coal handling plant area
8Find out the list of contractors and sub-contractors involved
8What kind of RFQs are still left to come
Click here for more details for project details and key contacts


**********************************