Mar 11: Phosphoric Acid Expansion Project 8Cost - Rs 1100 crore 8Project Event: The Detail engineering is ongoing, The purchase of a long lead item is ongoing. The project has been delayed however from its original schedule and the construction is likely to start in May 2019. Click here for more details Ammonia-Urea Energy Saving Project 8Cost - Rs 250 crore 8Project Event: The project has sufficient fund to progress but due to internal issues, the project is still on hold, RFQ for the contractor is likely to be released in April 2019. Click here for more details