Mar 07: 8Project Name: Manali Refinery BS-VI Upgradation Project
8Project Cost: Rs 497 crore
8Project Description: Chennai Petroleum Corporation Ltd along with ThyssenKrupp Industries India Pvt. Ltd as an EPCM contractor is currently undertaking contracting activities for a new FCC gasoline desulphurization unit with a capacity of 0.6 MMTPA and expansion of the DHDT unit from 1.8 MMTPA to 2.4 MMTPA at its Manali refinery. Find out who the subcontractors are. Know more on what kind of equipment are still required.
8Project Event: RFQ for the piping work for the DHDT unit and its mechanical offsite work is expected by May 2019.
8Expenditure Approval: Q4:2016
8RFQ Date: May/2019
8Release Date: May/2019
8Start Date: Q2:2017
8Completion Date: Q3:2019