Power Sector: Latest project news
Mar 06: Project Name: Hydroelectric Power Plant: RM&LE Project
8Project Cost: 300 crores
8Project Description: A DPR report is getting prepared for a renovation, modernization, and up-gradation of a hydropower project. A German financial agency has been withdrawn for the funding. Owner is in now look-out for a new funding agency. An EPC turnkey contractor bid is also ahead.
8Expenditure Approval: Q2:2019
8RFQ Date: Q3:2019
8Release Date: Q3:2019
8Start Date: 2020
8Completion Date: 2022
Click here for more details for project details and key contacts

8Project Name: Greenfield Pumped Storage Project
8Project Cost: 6000 crores
8Project Description: WAPCOS is carrying out site survey activities for a 1000 MW pumped-storage hydropower project. PFR has been approved by the Ministry of Water Resources. DPR works are expected to complete by mid-2020.
8Expenditure Approval: Q4:2018
8RFQ Date: May/2019
8Release Date: May/2019
8Start Date: 2021
8Completion Date: 2025
Click here for more details for project details and key contacts


**********************************