250 km infield pipeline order: RFQ pending
Feb 06: 8Project Name: Drilling Site Development
8Project Cost: Rs 2500 crore
8Project Description: The owner's RFQs for the hiring of an EPC contractor for the production installations and laying of 250 km infield pipeline is pending . Find out what is the latest status of the project
8Project Event: RFQ for hiring Rigs and other equipment is expected by April 2019
RFQ for hiring an EPC contractor for the production facilities and pipeline network is expected by May 2019
8Expenditure Approval: Q3/2017.
8RFQ Date: Apr/2019
8Release Date: May/2019.
8Start Date: Q4/2019
8Completion Date: Q4/2021