Dual feed rig to become operational
Feb 05: 8Project Name: Drilling Site Development
8Project Cost: Rs 30 crore
8Project Description:  The company is planning to implement a CNG based drilling rig pilot project instead of a diesel engine based rig for the development drilling. The modification for the company-owned drilling rig from diesel powered to dual fuel mode has been recently completed. For now, the owner will soon release the RFQs for the hiring of an EPC contractor for flowline installation at its GGS.
8Project Event: RFQ for hiring an EPC Contractor is expected by April 2019.
8Expenditure Approval: Jan/2018.
8RFQ Date: Apr/2019
8Release Date: Jun/2019. 
8Date: Apr/2019
8Completion Date: Dec/2020