Jan 15: 8Project Name: Panipat Refinery Naphtha Cracker Unit Expansion Project
8Project Cost: Rs 1636 crore
8Project Description: The latest status as drawn up by our internal team of engineers from our sources on the ground shows that the. HAZOP study for NCU, ERU & MEG has already been completed while the Safety Integrity Level study is in progress. Further RFQs are expected soon.
8Project Event: RFQ for the Enhanced Binary Refrigeration compressor, cold box is expected by March 2019.
RFQ for the coke removal system and Naphtha Cracker Unit heater is expected by April 2019.
8Expenditure Approval: Q4:2016
8RFQ Date: Mar/2019
8Release Date: Mar/2019
8Start Date: Q1:2019
8Completion Date: Q1:2021