Jan 09: 8Project Name: Drilling Field Exploration
8Project Cost: Rs 120 crore
8Project Description: The 3-well exploratory drilling programme in the North East has been delayed on account of amendments sought by the Environment Appraisal Committee (EAC). Owner-owned electrical type rigs are proposed to be deployed for undertaking drilling in the block. The equipment required for the project will be Drill Pipes, Casing Pipes, Xmas Trees, Blow Out Preventer, Cementing services and Drilling fluid services. Further RFQs are expected shortly.
8Project Event: RFQs for the hiring of equipment and oilfield chemicals are expected by May 2019.
8Expenditure Approval: Q3:2016
8RFQ Date: May/2019
8Release Date: May/2019
8Start Date: Q4:Dec/2019
8Completion Date: Dec/2022