Rs 800 crore worth of fertilizer projects: A status update
Jan 04: Ammonia Brownfield Project 8Cost - Rs 250 Crore 8Project Event: The project is in the initial phase and discussion is ongoing, RFQ for the process licensor is likely to be released in April 2019. The proposal for the environmental clearance is likely to be submitted in February 2019. Click here for more details Sulphuric Acid and Captive Power Unit Expansion Project 8Cost - Rs 300 Crore 8Project Event: Discussion process is ongoing, The project team is not been formed yet. Project activities are likely to start in February 2019. RFQ for the EPC contractor is likely to be released in March 2019. Click here for more details Ammonia-Urea Energy Saving Project 8Cost - Rs 250 Crore 8Project Event: The company is still waiting for capital approval, sources, however, said that the energy saving project will come up within the DOF-inspired timelines. Click here for more details