Dec 07: Phosphoric Acid Expansion Project
8Cost - Rs 1100 Crore
8Project Event: The basic engineering is ongoing, detailed engineering is likely to start in February 2019. RFQ for the long lead item is likely to be released in February 2019. The project has been the delayed and the construction is likely to be started in May 2019.
Click here for more details
SSP-Sulphuric Acid & NPK Fertilizer Expansion Project

8Cost - Rs 75 Crore
8Project Event: RFQ for a contractor is likely to be released after environmental clearance. The environmental clearance is due and it is likely to be elicited in February 2019. The RFQ for the EPC contractor is likely to be released in February 2019.