Power Sector: Future RFQs
Oct 22: Project Name: Greenfield Hydroelectric Power Project
8Project Cost: 810 crores
8Project Description: The civil package contractor is undertaking the removal of slide deposit in the desilting tank area for owner's 84 MW greenfield hydroelectric power station. Moreover, open excavation of the diversion channel is in progress. The H&M package contractor has signed a contract agreement on September 2018. Mobilization of hydro-mechanical equipment is to start by the next month. Further bids are expected soon.
8Project Event: RFQ for the erection of hydro-mechanical equipment is expected by December 2018.
8Expenditure Approval: Oct/2017
8RFQ Date: Dec/2018
8Release Date: Dec/2018
8Start Date: Q2:2018
8Completion Date: Q4:2021
Click here for more details

8Project Name: Thermal Power Station - FGD Addition
8Project Cost: 500 crores
8Project Description: The power generating company along with DPR consultant is carrying out the detailed project activities for installation of a wet flue gas desulphurization system at its 1000 MW unit thermal power complex. A pre-feasibility report has already been prepared. Further bids are expected soon.
8Project Event: RFQ for design, engineering, supply, erection, and commissioning of a wet FGD system is expected by the end of October 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: 26/Oct/2018
8Release Date: 28/Oct/2018
8Start Date: Q3:2019
8Completion Date: Q1:2021