Oct 22: Project Name: Greenfield Hydroelectric Power Project 8Project Cost: 810 crores 8Project Description: The civil package contractor is undertaking the removal of slide deposit in the desilting tank area for owner's 84 MW greenfield hydroelectric power station. Moreover, open excavation of the diversion channel is in progress. The H&M package contractor has signed a contract agreement on September 2018. Mobilization of hydro-mechanical equipment is to start by the next month. Further bids are expected soon. 8Project Event: RFQ for the erection of hydro-mechanical equipment is expected by December 2018. 8Expenditure Approval: Oct/2017 8RFQ Date: Dec/2018 8Release Date: Dec/2018 8Start Date: Q2:2018 8Completion Date: Q4:2021 Click here for more details 8Project Name: Thermal Power Station - FGD Addition 8Project Cost: 500 crores 8Project Description: The power generating company along with DPR consultant is carrying out the detailed project activities for installation of a wet flue gas desulphurization system at its 1000 MW unit thermal power complex. A pre-feasibility report has already been prepared. Further bids are expected soon. 8Project Event: RFQ for design, engineering, supply, erection, and commissioning of a wet FGD system is expected by the end of October 2018. 8Expenditure Approval: Q1:2018 8RFQ Date: 26/Oct/2018 8Release Date: 28/Oct/2018 8Start Date: Q3:2019 8Completion Date: Q1:2021 Click here for more details (Access to these links are available only those who have username and password to our sister publication, www.energylineindia.com)