Rs 190 crore Kadapa POL Depot Augmentation Project: An EPCM contractor will be required in November
Oct 16: 8Project Name: Kadapa POL Depot Augmentation Project
8Project Cost: Rs 190 crore
8Project Description:  Hindustan Petroleum Corporation Limited is planning to augment the depot,  install an intermediate pumping cum tap-off facility along with a receipt station and pigging facilities. Mantec Consultants Private Limited was appointed as PFR consultant. A slight delay has occurred in the selection of EPCM contractor due to delay in environment clearance. Further RFQs are expected soon.
8Project Event: RFQ for EPMC contractor is expected by November instead of August 2018.
8Expenditure Approval: Q2:2017
8RFQ Date: Nov/2018
8Release Date: Dec/2018
8Start Date: Q4:2018
8Completion Date: Q3:2021