Power Sector: Projects in pipeline
Oct 15: Project Name: Hydroelectric Greenfield Project
8Project Cost: 1150 crores
8Project Description: Owner along with an EIA consultant was accorded the environmental clearance in a 105 MW greenfield hydroelectric power project. The project is getting delayed due to pending techno-economic clearance from the CEA. The forest clearance is also outstanding at the state forest department. Further RFQs are expected soon.
8Project Event: RFQ for supply and erection of civil works and H&M works are expected by the Q1 2019.
8Expenditure Approval: Q1:2019
8RFQ Date: Q1:2019
8Release Date: Q1:2019
8Start Date: 2020
8Completion Date: 2025
Click here for more information
8Project Name: Thermal Power Plant - Dismantling Project 
8Project Cost: 210 crores
8Project Description: The Supreme Court of India mandated to shut down the owner's 850 MW operational thermal power plant with the commissioning of 400/220 kV sub-station. The sub-station will take the load off the TPS. The high-level committee of the owner is in discussion to dismantle the whole plant. Moreover, plans to implement a solar PV plant is still under a shadow. Further bids are expected soon.
8Project Event: RFQ for dismantling services of various equipment is expected by the Q1 2019.
8Expenditure Approval: Q4:2017
8RFQ Date: Q1:2019
8Release Date: Q1:2019
8Start Date: Q3:2019
8Completion Date: Q3:2020