200 MTPD LNG facility: Work is on
Oct 12: Ammonia-Urea Energy Saving Project       
8Cost - Rs 200 Crore
8Project Event: The Basic engineering and Detail engineering have been done by KBR and Tecnimont. Erection of NG lines to reformer, boiler & dual burner for auxiliary boiler has been completed. The purchase of a long lead item is ongoing. Land soil testing has been completed for the  200 MTPD LNG facility and civil construction is ongoing.