Oct 11: 8Project Name: Ennore POL Terminal Expansion Project 
8Project Cost: Rs 68 crore
8Project Description:  Bharat Petroleum Corporation Limited (BPCL) is planning to expand its an existing POL terminal from its existing capacity of 117035 Kilolitre to 157479 Kilolitre.Ultra -Tech Environment Consultancy & Laboratory for pre-feasibility studies. BPCL's TOR was rejected due to the submission of incorrect mapping configuration for clearance. The modification has now been done and BPCL has reapplied for the TOR on 4th October 2018. so a delay has occurred in the selection of EPC contractor. Further RFQs are expected soon.
8Project Event: RFQ for the EPC contractor is expected by December 2018.
8Expenditure Approval: Q3:2017
8RFQ Date: Dec/2018
8Release Date: Jan/2019
8Start Date: Q1:2019
8Completion Date: Q2:2020