Refinery Greenfield Naphtha Replacement Project: Equipment requirement coming up
Oct 01: 8Project Name: Refinery Greenfield Naphtha Replacement Project
8Project Cost: Rs 421 crore
8Project Description: The owner and the PMC contractor are revamping the Hydrogen Generation Unit (HGU) as well as modification in Gas Turbine and Boilers, which will lead to replacement of the use of Naphtha and Fuel oil with RLNG  
Requirement coming up: Major Equipment requirement coming up are for Boiler: Air coolers, Pumps, Vessels, Reactors & Vessels, Heat Exchangers, De-Superheater, Distributed control system and Bulk Items.
 
8Expenditure Approval: Q2:2017
 
8RFQ Date: Dec/2018
 
8Release Date: Jan/2019
 
8Start Date: Q1:2018
 
8Completion Date: Aug/2020