Apr 04: 8Project Name: Refinery Captive Power Greenfield Project 8Project Cost: Rs 1034 Crore 8Project Description: LSTK contractor is falling behind time installing a 66 MW Gas turbine based captive power plant at the refinery. Bid for civil work and related transportation services are on hold due to delay in preparation of Notice inviting tender. 8Project Event: RFQ for civil works and related transportation activities along with short lead equipment of gas turbine is expected by May 2018. 8Expenditure Approval : Q4:2016 8RFQ Date: May/2018 8Release Date: Jun/2018 8Start Date : Q4:2018 8Completion Date : Q4:2020 Click here for more details. 8Project Name: Greenfield petrochemical complex 8Project Cost: Rs5000 Crore 8Project Description: PMC contractor along with licensor is carrying out engineering activities to install a petrochemical complex. 8Project Event: The immediate RFQ which is coming up is for a centrifugal compressor and an integrally geared air compressor by May 2018. 8Expenditure Approval : Q2:2015 8RFQ Date: May/2018 8Release Date: Jun/2018 8Start Date : Q4:2015 8Completion Date : Q3:2019 Click here for more details. 8Project Name: LPG terminal expansion project 8Project Cost: Rs 700 Crore 8Project Description: The owner is planning to expand storage and handling of its LPG Terminal. Environmental Clearance is expected by July 2018. 8Project Event: RFQ for EPC contractor is expected by May 2018. 8Expenditure Approval : Q4:2017 8RFQ Date: May/2018 8Release Date: Jun/2018 8Start Date : Q3:2018 8Completion Date : Q4:2019 Click here for more details