Oct 18: 8Project Name: Greenfield 2G Ethanol Bio-Refinery 8Project Cost: Rs 900 Crore 8Project Description: An existing company along with licensor is planning to construct an ethanol plant based on the DBT-ICT 2G Ethanol technology developed indigenously to produce 100 KL fuel-grade ethanol per day, primarily from biomass and will use approximately 72 MTPD of biomass per year. 8Project Event: RFQ for a Project Management Consultant is expected by December 2017. 8Expenditure Approval: Q2:2017 8RFQ Date: Dec/2017 8Release Date: Jan/2018 8Start Date: Q1:2018 8Completion Date: Q1:2019 Click here for more details. 8Project Name: Exploratory Drilling 8Project Cost: Rs 710 Crore 8Project Description: Promoter is planning exploratory drilling of 18 wells on an onland block. The project involves exploratory drilling of 18 onshore wells and has been listed out as an extension project for an already existing 12 well drilling project. Currently, the project is in clearance phase. The environment clearance for the project is expected by Q1 2018. The forest clearance and CRZ clearance for the project is not required. RFQ for the following equipment are expected shortly: Cementing Unit, Blow Out Preventer, Pressure Gauge, Valves and Chemicals. 8Project Event: RFQ for the equipment is expected by December 2018. 8Expenditure Approval: Q3/2016 8RFQ Date: Dec/2017 8Release Date: Jan/2018 8Start Date: Feb/2018 8Completion Date: Q4/2022 Click here for more details