Oct 18: 8Project Name: Thermal Power Plant - FGD Addition 8Project Cost: Rs 680 Crores approximately 8Project Description: The owner is set to install FGD (Flue Gas Desulphurisation) units and upgrade ESPs (Electrostatic Precipitators) at its 1200 MW (2*600 MW) thermal power plant. At present, the feasibility studies are ongoing in consultation with NTPC and preparation of tender documents are expected to follow. The project is expected to kick off by the end of March, 2023. Commercially, RFQs for FGD installation and retrofitting of ESPs are expected to be out by the second quarter of 2019. 8Project Event: RFQs for FGD installation and retrofitting of ESPs are expected to be out by Q2, 2019. 8Expenditure Approval: 2016 8RFQ Date: Q2:2019 8Release Date: Q3:2019 8Start Date: Mar/2023 8Completion Date: Q4:2023 Click here for more information 8Project Name: Hydroelectric Greenfield Project 8Project Cost: Rs 500 crore 8Project Description: The owner along with consultant is carrying out the EIA/EMP report activities for scoping the environment clearance for a 80 MW ( 2*40 MW) greenfield hydel power project. TOR was accorded on 8 November 2012, and after its expiry, extension of validity of TOR was granted on 12 February 2015. Collection and study of required three seasons baseline data have been completed. Preparation of draft EIA/EMP reports are under progress. The project is getting delayed due to natural environmental factors, however the environmental clearance is likely to be elicited by Q2 2018. The developer will come out with an EPC package after getting EC. 8Project Event: RFQ for an EPC contractor is expected by Q3 2018. 8Expenditure Approval: Q1:2018 8RFQ Date: Q3:2018 8Release Date: Q4:2018 8Start Date: Q2:2019 8Completion Date: Q3:2023 Click here for more information 8Project Name: Thermal Power Maintenance Project 8Project Cost: Rs 10 crore 8Project Description: The owner has planned a 18-day Scheduled Mini Overhaul of Unit-9 B-TPS (200 MW) in the 1188 MW Thermal Power Plant covering a mini overhaul of the complete unit which includes turbine bearings,refilling of gas for HP, IP, LP turbine cylinders, motor winding, boiler linings, safety valves, nozzles, rotor blades, circuit breakers, relays, fuses, pipes, conveyor belts, bucker wheel, among others. 8Project Event: RFQs for equipment required in the maintenance are expected by 2nd week of November 2017. 8Expenditure Approval: Q2:2017 8RFQ Date: 15/Nov/2017 8Release Date: Dec/2017 8Start Date: 11/Feb/2018 8Completion Date: 28/Feb/2018 Click here for more information