Oct 06: 8Project Name: Greenfield Hydroelectric Project 8Project Cost: 800 crores 8Project Description: The owner along with the consultant is writing out the detailed project report for scoping the environment clearance for a 88.5 MW (3*29.5 MW) greenfield hydel project on BOOT basis. TOR has been accorded on 12 January 2015 which would be valid for five years. Baseline studies for hydrology and power potential studies have been approved by the CEA and CWC. DPR is in advanced stages of completion. Socio-economic survey, public hearing and detailed EIA report are pending and would take another 9 to 10 months for completion. The owner will come out with an EPC contract after getting EC. 8Project Event: RFQ for an EPC contractor is expected by fourth quarter of 2018. 8Expenditure Approval: Q2:2018 8RFQ Date: Q4:2018 8Release Date: Q4:2018 8Start Date: Q2:2019 8Completion Date: Q3:2023 Click here for more information