Software updates: Power projects
Aug 31: 8Project Name: Hydroelectric Greenfield Project
8Project Cost: Rs 875 crore
8Project Description: The owner along with a consultant is writing out the final EIA report for scoping environment clearance for a 90 MW (3*30 MW) greenfield hydroelectric project. The TOR has been extended. Implementation of Social Impact Assessment and Public Hearing are pending and will be completed after getting NBWL permission. Environment Clearance is likely to elicited within 4 months.
8Major equipment that will be required will be three Francis Turbine, Radial gates, turbine-generator sets and associated auxiliaries, transformers, butterfly valves, turbine auxiliaries, governors with auxiliaries, cables, bus ducts and terminal equipment, EOT cranes, shaft and bearing, couplings, vibration control system, girders, tunnel boring machine, powerhouse equipment, among others.
8Project Event: RFQ for an EPC contractor is expected by 1st Quarter of 2018.
8Expenditure Approval: Q4:2017
8RFQ Date: Q1:2018
8Release Date: Q1:2018
8Start Date: Q2:2018
8Completion Date: Q3:2023
Click here for more information

8
Project Name: 
Captive Plant Expansion
8Project Cost: Rs 984 Crores
8Project Description: The owner is planning to add 165 MW to its captive capacity of 40 MW. TOR was granted to this project and at present surveys are ongoing at the site. The capacity addition is planned in the following manner 40 MW through coke oven (CO) gas, 68 MW through waste heat recovery unit (WHRU), 22 MW through blast furnace gas (BFG) type boiler and 35 MW through coal based AFBC boiler unit. RFQs for Civil works, Electrical and Mechanical Package, Control & Instrumentation units and BoP are expected in late 2018. 
 Major equipment required will be waste heat recovery unit (WHRU) boilers, atmospheric fluidized bed combustion (AFBC) boiler, blast furnace gas (BFG) boiler, turbines, turbine generators, piping and fitting, pumps, valves, control unit, governor, DG set, electrostatic precipitator (ESP), cooling water circulation system, transmission lines, cables, insulation work, lubrication system and heat exchangers among others.
8Project Event: RFQs for Mechanical equipment expected in the last quarter of 2018.
8Expenditure Approval: 2016
8RFQ Date: Q4:2018
8Release Date: Q1:2019
8Start Date: Q4:2019
8Completion Date: 2022
Click here for more information


**********************************