Software updates-II: Rs 3470 crore development drilling project coming up
Aug 17: 8Project Name: Development Drilling project 8Project Cost: Rs. 3470 crore 8Project Description: An E&P company is planning development drilling of 89 wells. The project also involves 9 production installations and laying of a pipeline. The EIA consultant has not been finalized as of now. Currently, geological surveys are going on. The project has not been granted wildlife clearance as of now. Environmental clearance for the project can be expected by Q2 2018. Further RFQs can be expected in upcoming months. 8Project Event: RFQs for the mechanical equipment is expected by June 2018. 8Expenditure Approval: Q3:2016 8RFQ Date: Jun/2018 8Release Date: Jul/2018 8Start Date: Aug/2018 8Completion Date: Sep/2021 Click here to go to our software for more information.