FSRU and FSU units coming up-II: Schedule of work
Jan 03: The construction phase of the project is expected to start from Q-2,2017.
The project schedule involves:
8Investigation Studies-6 Months
8Jetty Construction-18 Months
8FSRU Conversion-15 Months
8Onshore storage tanks-36 Months
8Regasification facilities-8 Months
8Truck Loading Stations-6 Months
8Dredging Activity-6 Months
8Unloading Arms-6 Months
8Gas Pipeline Connectivity-12 Months
8The project is expected to get commissioned in February, 2020.