Dec 21: A three-phase 10 MMTPA expansion of an existing refinery is now coming up.
8Environmental clearance is expected to be granted in December, 2017.
8The expansion includes in phases additional units, including a CDU, a Fluid Catalytic unit and a DHT unit as well as other units.
8The expansion is likely in three phases and the entire expansion will be commissioned by 2022.
The following equipment requirements:
8Columns, Condensors, Feed water exchangers, Feed water tanks, Heat Exchangers, Heaters, Piping, Pressure Vessels, Reactors, Scrubbers, Flakers, Smoke Duets, Smoke Washers, Steam Drums, Storage Reactors, Reactors With Agitators, Post-Processors, Reactors, Regenarator, Fractionators, Settler, Reflux drums, Air fin cooler tubes, Pumps, Plates, Nozzles, Vessels, Columns cyclones, Air blowers, Wet gas compressors, Relief valves, boilers, Electrostatic precipitators, Scrubbers, Bellows, Heat exchangers, Switch condensers, Intercoolers, Stripping Columns, Separating columns, Other welded construction parts 