Cambay drilling: Details
Nov 17: Drilling and testing of 4 wells of around 2000 to 2500 meters have been done by now out of  an eight well onland drilling programme in the Cambay Basin.
8Environment clearance was granted to the project in October,2015.
8Drilling of the 5th well is going to start by next week, around November 23, 2016.
8The entire drilling programme is expected to be completed by June, 2017.
8Cost of the project is around Rs 165 crore
8The look out will then be for well testing and development drilling opportunities