All content in this website is sourced legitimately

Article Details
Page No:  1
TAPI: Business prospects opening up?
Mar 24:   A consultant has been appointed for Front End Engineering Design (FEED) and other pre-project activities for the Turkmenistan-Afghanistan-Pakistan-India (TAPI) gas pipeline project.
8The project cost is now pegged at $ 15 billion.
8It will be a 56 inch diameter pipeline with a total estimated length of 1814 km and it will transport 90 MMSCMD of natural gas, of which 38 MMSCMD is for India.
8The overall TAPI project duration is estimated to be 7 years from the start of the Front End Engineering Design (FEED) process till handling over of the pipeline for commercial operation.
8Business development prospects are emerging in the project, it looks like
Click on Reports for more
 Details

**********************************

<< Back  |  Top
 
The content in this website is authentic and all information is sourced legitimately. The news we produce is collated through journalistic effort that is legal and legitimate. We carry no information that violates Indian law or is a breach of confidentiality in any form or manner.
Copyright 2017 www.indianpetroplus.com. All rights reserved