Software updates: Oil and Gas Projects.
Dec 08: 8Project Name: Refinery IndJet Unit Moderization Project
8Project Cost: Rs 145 Crore
8Project Description: An existing company along with EPCM contractor is planning to install a new IndJet unit to produce 250 KTA of Aviation Turbine Fuel (ATF) and 75 KTA of Pipeline Compatible Kerosene (PCK) from its Refinery. Engineers India Limited (EIL) has been entrusted to carry out the Environmental Impact Assessment (EIA) and Risk Analysis/Assessment (RA) studies for the project. TOR was granted on 8 June 2017 and EC is expected by January 2018.
8Project Event: RFQ for major equipment is expected by January 2018.
8Expenditure Approval: Q2:2017
8RFQ Date: Jan/2018
8Release Date: Mar/2018
8Start Date: Q1:2018
8Completion Date: Q4:2020
Click here for more details.
8Project Name: Pipeline Expansion Project
8Project Cost: Rs 400 Crore
8Project Description: An existing company along with EPCM contractor is planning to expand its pipeline from 4.71 MMTPA to 7.11 MMTPA. They are also planning to install a new pumping station which will be constructed with separate booster pumps for POL & LPG along with mainline pumps. There will also be a new intermediate pumping station at SV4 which will be constructed along with a separate mainline pump for the expansion.
8Project Event: RFQ for equipment is expected by January 2018.
8Expenditure Approval: Q1:2017
8RFQ Date: Jan/2018
8Release Date: Mar/2018
8Start Date: Q1:2018
8Completion Date : Apr:2019
Click here for more details.


**********************************