Software updates: Oil and Gas Projects.
Oct 10: 8Project Name: Greenfield LPG Bottling Plant
8Project Cost: Rs 155 Crore
8Project Description: An existing company is planning to construct an LPG bottling plant with a capacity of 44 TMTPA.
8Project Event: RFQ for a Project Management Consultant is to be expected by February 2018.
8Expenditure Approval : Q2:2017
8RFQ Date : Feb/2018
8Release Date: Mar/2018
8Start Date : Q2:2018
8Completion Date : Q2:2020
Click here for more details.
8Project Name: Additional Tankage POL Terminal Project
8Project Cost: Rs 9 Crore
8Project Description: An existing company is planning to expand its capacity by constructing a new Ethanol tank with a capacity of 1600 KL. The capacity will then go up from 76017 KL to 77617 KL.
8Project Event: RFQ for Project Management Consultant is to be expected by December 2017.
8Expenditure Approval : Q2:2017
8RFQ Date : Dec/2017
8Release Date: Jan/2018
8Start Date : Q2:2018
8Completion Date : Q2:2019
Click here for more details.
8Project Name: Oilfield Development Drilling
8Project Cost: Rs 370 Crore
8Project Description: Promoter is planning the development drilling of oil wells in a Mining Lease Block.The project is listed out as an expansion project for the already existing 20 wells development drilling project. Currently, the well fluid collection and testing facilities for Tanot Field are located at existing GGS and GPC, each having a Gas processing capacity of 1 MMSCMD and 0.4 MMSCMD respectively. The rig package and pipeline contract are in the final stage of award.  RFQs for all well consumables and production equipment, namely X-Mas trees, Tubing Head Spools, Hanger Flanges / Tubing Hangers, Separators with all accessories, Steam Jacket, Ground X-Mas tree, Tubing Pipes for surface fittings and flare line etc. are expected shortly.
8Project Event: RFQ for hiring civil contractor for construction works is expected by end October 2017.
RFQ for equipment is expected by November 2017.
8Expenditure Approval: Q4/2016
8RFQ Date: Oct/2017
8Release Date: Nov/2017
8Start Date: Jun/2018
8Completion Date: Q2/2021
Click here for details


**********************************