Jan 11: Ammonia-Urea & Captive Power Plant Greenfield Project
8Cost - Rs 10741 Crore
8Project Description:  A Fertilizer Company is planning a greenfield coal-based ammonia-urea plant with a capacity 2200 MTPD of ammonia, 3850 MTPD of urea and 70 MW of Captive power plant. The consultant and process licensors have been appointed. The tender is out for the LSTK contractor.
8Project Event: RFQ for LSTK contractor was floated in May 2017 and the bid closing date for Coal Gasification Plant for Generating Ammonia Syn. Gas & Carbon Dioxide Gas is extended from 26 November 2017 to 28 February 2018 and the ammonia-urea plant is extended from 9 January to 8 March 2018.
Click here for more information
Ammonia-Urea Energy Saving Project   
8Cost - Rs 481 Crore
8Project Description: Thermax, BHEL, Sterling & Wilson are in the race for an energy saving project of Rashtriya Chemical and Fertilizer Ltd at its Trombay Fertilizer Complex in Mumbai. Rashtriya Chemical and Fertilizer Ltd is planning to reduce the energy consumption of its Ammonia and Urea units from 8.73 Gcal/MT to 8.40 Gcal/MT and 6.75 Gcal/MT to 6.45 Gcal/MT respectively in India. The capacity of the ammonia plant is 1045 MTPD and the urea capacity is 1000 MTPD. The equipment requirements are 2 nos of GTG with a capacity 25 MW (ISO Rating), 2 nos of HRSG with a capacity 65 TPH, Replacement of turbine for the Benfield Solution Pump in Ammonia with a new motor, De-aerator (2 nos.) with HP BFW Pump motor set 2 x (1+1), One PRDS system for 12 ata to 4.5 ata in the Ammonia plant, Modification in Power Distribution System. Environment clearance is awaited and it will take about three months.
8Project Event: The selection process for the LSTK contractor is on and techno-commercial discussion is completed and price bid is likely to be opened by the end of January 2018