Feb 01: Contractor to look for FGD package
8Project Name: Thermal Power Station - FGD Addition
8Project Cost: 700 crores
8Project Description: The owner is planning the installation of a Flue Gas Desulphurization (FGD) unit at it's 1500 MW (6*250 MW) unit Thermal Power Station. The company is expected to float tenders for the same. At present, site survey activities have been carried out for the feasibility report for submission to CEA for approval. Work on the project is meant to start in 2020. RFQ for supply of FGD is expected to be out by Q3 2018.
8The major requirements will be FGD, stacker and reclaimer, cranes, pipes, gypsum disposal, limestone, absorber, among others.
8Project Event: RFQ for supply of FGD is expected to be out by Q3 2018.
8Expenditure Approval: Q3:2017
8RFQ Date: Q3:2018
8Release Date: Q4:2018
8Start Date: 2020
8Completion Date: 2022
Click here for more information
RFQ for hydro power maintenance coming up shortly
8Project Name: Hydro Power Maintenance Project (Unit - 8)
8Project Cost: 15 crores
8Project Description: The promoter has planned a 15-day scheduled maintenance of Unit-8 (65 MW) in the 520 MW Hydro Power Station, covering overhauling of auxiliary parts of the turbine and its blade sets, seals, and the oil cooling unit.
8Equipment required will be turbine bearings, gland seals, spiral casing, replacing of worn out rubber flaps, among others.
8Project Event: RFQ for equipment is expected by mid of February 2018.
8Expenditure Approval: Q2:2017
8RFQ Date: 11/Feb/2018
8Release Date: 28/Feb/2018
8Start Date: 16/Mar/2018
8Completion Date: 30/Mar/2018