Software Updates : 60-day shutdown coming up
Jan 12:   8Project Name: Thermal Power Plant Maintenance Project (Unit-1)
8Project Cost: 25 crores
8Project Description: The owner has planned a 60-day scheduled maintenance of Unit-1 (660 MW) in the 1320 MW (2*660 MW)  covering an annual maintenance of equipment which includes overhauling of auxiliary parts of turbine, boiler, generator comprising HP, IP, LP cylinders gas testing, testing and cleaning of condenser parts, Residual Life Assessment of boiler pressure parts, assessing performance and condition monitoring of the furnace, mills, APH and associated ducts.
8Equipment required will be air filters, boiler tubes, buckstays, chevron blades, condenser tube banks, thrust bearing, journal bearings, among others.
8Project Event: RFQs for short lead equipment required are expected by February 2018.
8Expenditure Approval: Q2:2017
8RFQ Date: Feb/2018
8Release Date: Feb/2018
8Start Date: 13/Mar/2018
8Completion Date: 11/May/2018  Details

**********************************