Rs 900 crore private sector shale well programme: Hydrofracturing unit RFQ in Q4
Jun 04: 8Project Description: The Promoter is planning exploratory drilling of 35 shale gas and oil wells. The wells are expected to be drilled up to a depth of 4400 meters. Promoter owned drilling rigs are proposed to be deployed for undertaking drilling activities. An EIA report has been already submitted for obtaining environment clearance. The equipment required for the project will be Hydrofracturing Equipment, Proppant, Casing pipes, Drilling pipes, Blow out preventer, Cementing services, Drilling fluid services and other oilfield chemicals.
8Project Event: RFQ for the hydrofracturing unit and other equipment and oilfield chemicals are expected by Q4:2018.
8Expenditure Approval: Q2/2014
8RFQ Date: Q4/2018
8Release Date: Q4/2018
8Start Date: Feb/2020
8Completion Date: Dec/2022