Rs 400 crore Sea Water Reverse Osmosis Desalination Project: RFQ by August.
May 17: 8Project Name: Onshore Processing Plant
8Project Cost: Rs 400 crore.
8Project Description: The owner's RFQs for ta Sea Water Reverse Osmosis Desalination Project at the facility have been delayed on account of the financial review of the project. A cost revision is expected for the project, as the current estimate is significantly on the lower side. The environmental clearance and the CRZ clearance for the project have already been granted.
8Project Event: RFQs for hiring an LSTK contractor is expected by August 2018 instead of June 2018.
8Expenditure Approval: Q1/2016.
8RFQ Date: Aug/2018.
8Release Date: Sep/2018.
8Date: Q4/2018
8Completion Date: Q4/2019