Root causes of time and cost overrun in big projects: Changing dynamics
Mar 06:   This all-India analysis of project performance has narrowed down the root causes of time and cost over run in these projects
8Cost parameters which were not all that important earlier are now gaining precedence, such as high cost of environmental safeguards and spiraling land acquisition cost
8Delay in land acquisition is on top the list when it comes to time over run as well as delays in obtaining environmental clearance