Apr 17:   8Project Name: Oil Field Development
8Project Cost: Rs 8000 crore
8Project Description: Promoter has planned development drilling of oil wells. The project is expected to be rolled out in several phases, with first phase involving development drilling of 70 wells. Requirements for the project are:- drill pipes, drill casings, diesel gensets, drilling fluid, chemical additives, rigs.
8Project Event: RFQs for hiring drilling rig and wireline services is expected by June 2018.
 RFQs for the mechanical equipment are expected by end of June 2018 instead of March 2018 as was project earlier.
8Expenditure Approval: Q3/2016
8RFQ Date: Jun/2018
8Release Date: Jul/2018
8Start Date: Q4/2018
8Completion Date: Q2/2025
Click here for more information related to the project and along with key owner contacts
 Details

**********************************

Back  |  Top
 
The content in this website is authentic and all information is sourced legitimately. The news we produce is collated through journalistic effort that is legal and legitimate. We carry no information that violates Indian law or is a breach of confidentiality in any form or manner.
Copyright 2018 www.indianpetroplus.com. All rights reserved