Our project software-IV: Upstream updates
Aug 14: 8Project Name: Exploratory Drilling
8Project Cost: Rs 2500 crore
8Project Description: An E&P major planning exploratory drilling of 50 wells. The environmental clearance for the project is expected by the Q3, 2018. The drilling of the wells is expected to be up to a target depth of 3000 meters below ground level.
8Project Event:  RFQs for the long lead items can be expected by the Q4 2018.
8Expenditure Approval: 2013
8RFQ Date: Q4:2018
8Release Date: Q4:2018
8Start Date: Q1:2019
8Completion Date: Q4:2021
Click here for more
8Project Name: Development Drilling
8Project Cost: Rs 283.92 crore
8Project Description: An E&P company is planning development drilling of 6 wells The project would also involve the conversion of 3 exploratory wells into development wells, upgradation of the GCS and laying of a 10" pipeline (42 Km) from the wells to the GCS. The project is in the pre-clearance phase.
8Project Event: The RFQs for hiring consultant for EIA services is expected by September 2017. 
8Expenditure Approval : Q3:2016
8RFQ Date: Sep/2017
8Release Date: Oct/2017
8Start Date: Q4:2018
8Completion Date: Q3:2020