LNG terminal coming up-III: TImeslines
Dec 21:   The following timelines have been set for the project
81st phase: 6 months after all statutory permissions.
8Dredging Services: 10 months through cutter suction dredgers, simultaneously after  EC approval.
8Total project commissioning: 16 Months after the start of construction work.
The following is the cost segregation of the project:
8Floating assets - Rs 1950 crore
8Land and land development - Rs10 crore
8Dredging - Rs 200 crores
8Shore Protection - Rs 120 crore
8Berth Construction - Rs 100 crore
8Marine equipments-topsides - Rs 100 crore
8Onshore civil, pipelines, services & utilities - Rs 100 crore
8Preliminary & pre-operative - Rs 100 crore
Click on Details for more
 Details

**********************************

<< Back  |  Top
 
The content in this website is authentic and all information is sourced legitimately. The news we produce is collated through journalistic effort that is legal and legitimate. We carry no information that violates Indian law or is a breach of confidentiality in any form or manner.
Copyright 2017 www.indianpetroplus.com. All rights reserved