All content in this website is sourced legitimately

Article Details
Page No:  1
Business development opportunities
Mar 20:   POL storage: TOR expected by June, 2017
8PFR has been already done. Construction of three new product storage tanks and associated facilities for storage & handling of ethanol & bio-diesel is about Rs. 17.01 crore. RFQs are expected
A new 2G Bio Ethanol refinery is coming up:
Consultant to be hired soon
8Capacity of 2G Bio Ethanol Refinery will be 100 KLPD. The likely feedstock for 2G Ethanol Bio-refinery would be 
-- Soya husk 
-- Wheat straw
-- Corn cobs.
Expansion work in DHDS unit: RFQs will be floted by April,2017
8Expansion of 0.54 MMTPA in a DHDS unit. Phase 1 The cost of the proposed project is Rs. 367.11 crore
New product pipeline is coming up: RFQs will be floated by May, 2017
8EC is granted for the project. Total costing of the project is Rs. 640 crore
Click on Reports for more
 Details

**********************************

<< Back  |  Top
 
The content in this website is authentic and all information is sourced legitimately. The news we produce is collated through journalistic effort that is legal and legitimate. We carry no information that violates Indian law or is a breach of confidentiality in any form or manner.
Copyright 2017 www.indianpetroplus.com. All rights reserved