30-well onland drilling programme-I: RFQs for GCS and in-well pipeline in April, 2017
Nov 17:   Environment clearance is expected in June, 2017 for a 30 well onland development programme.
8Within this project, the cost of Gas Compressor Station (GCS) and in-well pipeline laying is Rs. 200 crore.
8RFQs are expected in April, 2017